Project was to Sink a 16mtr elevator shaft in a heritage building in the mall of Brisbane city, the method that we used was to excavate the rock...
The project was to develop a 18mtr access tunnel inside the elevator shaft inside Mcarther chambers heritage buildings, the tunnel was constructed...
Development of 12mtr access tunnel under the casino, the tunnel was in sand and canopy tubes were installed and grouted before excavation could proceed.Walls...
Development of lift well shaft for high rise building, method using rock splitter and Jack hammers, in the heart of Townsville. 
Drilling of blast holes in road construction, and drilling of blast holes for the open cut nickle mine 
Civil works in Carter st Townsville in very a sensative area, units were at 10 mtrs away, cardox was used to break the hard pink granite, no permits...
Development of a 300mtr exploration tunnel in the Goiala provence Papua new Guinea. 
Project was drill and blast and standing of wooden sets,...
Supply Mining equipment and personell for open cut development at Ravenswood project for Hioma Mining Ravenswood, operation was to remove material...
Development of the Kainantu gold mine's project Papua New Guinea, development of portals and underground workings and stopeing blocks. 
All...
Supply experianced personell to carry out the Blasting services on the road construction Project, for the Australian Army 
 